Spring Maintenance Is Underway for the Year
Most roads were graded and were looking much better, but then more snow fell which basically turned the roads to mudded ruts again. In the future Spring Maintenance should not happen until after May 15th at the earliest.
Discussion determining where new material will be added will take place at the regular May 13th Board Meeting
A three phased approach was approved -
1) Dry Blade the primary roads as well as Buck - this pulled up a lot of the already present gravel - completed 5/23/2025
2) Depending on results of the dry blading, additional gravel composed of a single wash and screened mix of material may be added to areas that remain the muddiest - primarily the Entrance and up SaddleBack to the bottom of the hill or top depending on costs and needs. Also the corner of Loma Linda starting a San Juan and heading around the corner to the driveway of 1265 Loma Linda Dr.
3) Mag Chloride will be added when possible